Update to the Kerry Central RWSS Project

Update – January 2017
The project is close to 40% complete, all major civil engineering aspects of the project are proceeding as planned and are ahead of the project programme. The 6,000m3 capacity reinforced concrete tanks are now complete, fully tested and backfilling around the structure will commencein the coming days. The Process tanks and water treatment building have now started and are proceeding as per programme. The sludge farm reinforced concrete elements are now complete and awaiting the installation of the sludge plate press in the coming week.