Projects Network Rehabilitation

UCD Watermain Upgrade and Remedial Works

UCD Watermain Upgrade and Remedial Works

Client:  University College Dublin

Location:  UCD, Belfield, Dublin 4.

Date:  August 2011- September 2011

Contract Value: € 40,000

Client Representives:  University College Dublin

The UCD Watermain Upgrade and Remedial Works project involved the construction, testing and commissioning of new watermains on the campus of UCD, Belfield. The main scope of the work included;
  • Working on a Live College Campus
  • Decommissioning of existing hydrants (7 No.)
  • 160m of Pipe-laying in verges, roads and fields
  • Pipeline and PE welded joints testing
  • Trench dewatering
  • Temporary and permanent reinstatement
  • Connections to existing ‘live’ distribution system
  • Commissioning works include facilitating full change over to new works and decommissioning of existing works
  • Temporary traffic management